Secondary Proportionality

German Translation

Sekundärproportionale Fortschrittsmessung

Category

Project Management with SAP R/3

Short Description

Measurement technique used to determine the percentage of completion (POC) in progress analysis.
With this technique, the performance of a project object is dependent upon the progress of another project object.
Example:
In a network there are two activities, create engineering drawings and check drawings. A drawing is only complete once it has been checked.
The percentage of completion for the activity check drawings is taken from the activity create engineering drawings when you use this measurement technique.