Studierende stehen vor dem LC und blicken lächelnd einer Kollegin mit einer Mappe in der Hand nach.

Exercise No. 23: Product Launch

Transfer the following verbal description into an EPC

a) To launch/relaunch a product, the design department needs to prepare a raw design according to the product specification using the CAD-system.

b) Once the raw design is completed, the following departments test if the product meets their requirements: the sales, the manufacturing, the purchasing, and the quality control department.

c) Should the tests fail in one of the departments, then the raw design is revised and the modified product is tested again by all departments.

d) Once the tests are successful, the departments give instructions to prepare the final design. Thereafter the drafting department prepares the final design.

e) The finally drafted product is tested like the raw design (see b).

f) After successfully testing the drafted product, the drafting department prepares the documentation and the process is completed.